This Facility is located in Denver, Colorado. Everything shown in the
pictures was installed by APF. Inc.
This included
setting of all the
structural steel and silo, conveyors
and catwalks, handrails and gaurdrails,
beltcovers,
dust collection binvent on top of silo, gearboxes for conveyors,
and all necessary air and electrical
to run equipment.
In fact this was
solely being used as a warehouse when we
arrived on-site.
above are some great views of just what was starting
on the outside, on the right
Buck wonders if it'll
ever end. (more below).
above
is the last few pieces of tin going up on the main tower.
above
is a view of some of the other outside work that we
preformed.
(i.e. setting
all blocks for bins,conveyor
controls)
above
a couple
of snap shots from our work on the interior (last
photo we even installed the
tiled floor
seen under
control panel that was throughout the controlroom)
Note
(first photo notice the copper pipe
running below all others this is
the only project that was subbed out locally) the engineer
thought we
were
too busy.....Lol....!
above shows
production starting up! What a job! It took nothing short
of blood sweat and
tears.
Well maybe the ocassional
choice word here or there too, but once
again it was a job
well done by
everyone involved. For our guys that may
visit the site heres to you world wide style Job Well Done
and we Gone!!!!!
"We've done so much with so
little for so long."
"We can do almost anything with
nothing."